DEKALB COUNTY, GA— Weather permitting, the Georgia Department of Transportation (Georgia DOT) construction partners will temporarily close interstate lanes at the locations below for the I-285/I-20 East Interchange project. The project will reconstruct the interstate system-to-system ramps at the I-285/I-20 East Interchange and add a combination of collector-distributor, or connecting lanes, and auxiliary lanes along I-20 east of the interchange and I-285 north of the interchange.
Where/When:
I-20 from Wesley Chapel Road (MM 69.5) to Panola Road (MM 71.3)
- Monday, Sept. 23, through Friday, Sept. 27, from 9 a.m. to 2 p.m. (Daily)
Single, right-lane and shoulder closure on I-20 eastbound
I-20 from Panola Road (MM71.3) to Wesley Chapel Road (MM 69.5) (Nightly)
- Sunday, Sept. 22, through Saturday, Sept. 28, from 9 p.m. to 5 a.m. (Nightly)
Single, right-lane and shoulder closure on I-20 westbound
I-20 eastbound from the I-285 Interchange (MM 67.3) to Wesley Chapel Road (MM 69.5)
- Monday, Sept. 23, through Saturday, Sept. 28, from 9 a.m. to 2 p.m. (Daily)
Single, right-lane and right-shoulder closure on the connecting lanes or collector-distributor (CD) lanes
I-20 from Columbia Drive (MM 66.8) to the I-285 Interchange (MM 67.3)
- Monday, Sept. 23, through Saturday, Sept. 28, from 9 a.m. to 2 p.m. (Daily)
Single, right-lane and right-shoulder closure on I-20 eastbound
I-20 from Panola Road (MM 71.3) to the Fairington Road overpass (MM 72.6)
- Monday, Sept. 23, through Friday, Sept. 27, from 9 a.m. to 2 p.m. (Daily)
Single, right-lane and right-shoulder closure on I-20 eastbound
Hillandale Drive eastbound from east of Panola Road to DeKalb Medical Parkway
- Monday, Sept. 23, through Friday, Sept. 27, from 9 a.m. to 3 p.m. (Daily)
Flagging operation
I-20 from Panola Road (MM 71.4) to Wesley Chapel Road (MM 69.3)
- Monday, Sept. 23, through Saturday, Sept. 28, from 11 p.m. to 5 a.m.
Alternating, double, left- and right-lane and shoulder closures on I-20 eastbound and westbound
I-20 from the westbound ramp to I-285 northbound (Exit 67B)
- Monday, Sept. 23, through Saturday, Sept. 28, from 11 p.m. to 5 a.m. (Nightly)
Traffic pacing operation on the I-20 westbound ramp
I-285 southbound exit ramp to the I-20 eastbound ramp
- Monday, Sept. 23, through Saturday, Sept. 28, from 11 p.m. to 5 a.m. (Nightly)
Single, left-lane and left-shoulder closure on the connecting lanes
I-20 from the I-285 Interchange (MM 67.3) to Wesley Chapel Road (MM 69.3)
- Monday, Sept. 23, through Saturday, Sept. 28, from 11 p.m. to 5 a.m. (Nightly)
Alternating, double, left- and right-lane closures on I-20 eastbound and westbound
I-20 from the I-285 Interchange (MM 67.3) to Wesley Chapel Road (MM 69.5)
- Monday, September 23, through Saturday, Sept. 28, from 11 p.m. to 5 a.m. (Nightly)
Traffic pacing operation on I-20, both eastbound and westbound
I-20 from Panola Road (MM 71.3) to the Fairington Road overpass (MM 72.6)
- Monday, Sept. 23, through Saturday, Sept. 28, from 11 p.m. to 5 a.m. (Nightly)
Alternating, double, left- and right-lane closures on I-20 eastbound and westbound
I-20 from Columbia Drive (MM 66.8) to Panola Road (MM 71.3)
- Tuesday, Sept. 24, through Thursday, Sept. 26, from 1 p.m. until 2:30 p.m. (Daily)
Traffic pacing operation on I-20 eastbound, traffic will be held for up to five minutes
I-20 entrance ramps at Panola Road (MM 71.6) and Wesley Chapel Road (MM 69.5)
- Tuesday, Sept. 24, through Thursday, Sept. 26, from 1 p.m. until 2:30 p.m. (Daily)
Traffic pacing operation on I-20 westbound, traffic will be held for up to five minutes
I-20 from the I-285 Interchange (67.3) to Miller Road (69.8), including the westbound entrance ramp from Wesley Chapel Road (Exit 68)
- Monday, Sept. 23, through Saturday, Sept. 28, from 11 p.m. to 5 a.m. (Nightly)
Traffic pacing operation on I-20 eastbound and westbound
I-20 from Panola Road (MM 71.4) to Wesley Chapel Road (MM 68.5)
- Monday, Sept. 23, through Saturday, Sept. 28, from 9 p.m. to 6 a.m. (Nightly)
Alternating, single, left- and right-lane and shoulder closures on I-20 eastbound and westbound
I-20 from Panola Road (MM 71.4) to Wesley Chapel Road (MM 68.5)
- Monday, Sept. 23, through Saturday, Sept. 28, from 11 p.m. to 5 a.m. (Nightly)
Alternating, double, left- and right-lane and shoulder closures on I-20 eastbound and westbound
Activity | Start Date | End Date | Times | |
I-20 Westbound | ||||
|
Single, right-lane and right-shoulder closure | 9/22/24 | 9/28/24 | 9 p.m. – 5 a.m. |
|
Traffic pacing operation | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
|
Alternating, double, left- and right-lane and shoulder closures | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
|
Traffic pacing operation | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
|
Alternating, double, left- and right-lane closures | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
|
Alternating, double, left- and right-lane closures | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
|
Traffic pacing operation | 9/24/24 | 9/26/24 | 1 p.m. – 2:30 p.m. |
|
Traffic pacing operation | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
|
Alternating, single, left- and right-lane and shoulder closures | 9/23/24 | 9/28/24 | 9 p.m. – 6 a.m. |
|
Alternating, double, left- and right-lane and shoulder closures | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
I-20 Eastbound | ||||
|
Single, right-lane and shoulder closure | 9/23/24 | 9/27/24 | 9 a.m. – 2 p.m. |
|
Single, right-lane and right-shoulder closure | 9/23/24 | 9/27/24 | 9 a.m. – 2 p.m. |
|
Traffic pacing operation | 9/23/24 | 9/28/24 | 11 p.m. – 5.a.m. |
|
Single, right-lane and right-shoulder closure | 9/23/24 | 9/28/24 | 9 a.m. – 2 p.m. |
|
Single, right-lane and right-shoulder closure | 9/23/24 | 9/28/24 | 9 a.m. – 2 p.m. |
|
Alternating, double, left- and right-lane and shoulder closures | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
|
Alternating, double, left- and right-lane closures | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
|
Traffic pacing operation | 9/24/24 | 9/26/24 | 1 p.m. – 2:30 p.m. |
|
Traffic pacing operation | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
|
Alternating, single, left- and right-lane and shoulder closures | 9/23/24 | 9/28/24 | 9 p.m. – 6 a.m. |
|
Alternating, double, left- and right-lane and shoulder closures | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
I-285 Southbound | ||||
|
Single, left-lane and left-shoulder closure | 9/23/24 | 9/28/24 | 11 p.m. – 5 a.m. |
Hillandale Drive Eastbound | ||||
|
Flagging operation | 9/23/24 | 9/27/24 | 9 a.m. – 3 p.m. |