DEKALB COUNTY, GA— Efforts to improve the watershed system throughout DeKalb County continue Wednesday, May 20, with the launch of the Shoal Creek Trunk Sewer Replacement Project, Section I. Crews will replace 19,755 linear feet of aging pipelines. Section I of the sewer replacement project is expected to last approximately three years (May 2026 to September 2029), barring any weather or unexpected delays. The project, which will involve several stages in its entirety, is expected to take 9 years from start to finish, officials project.
Normal construction hours will be from 7 a.m. to 7 p.m., Monday through Friday, excluding major holidays. An increase in construction-related noise and traffic during work hours should be expected.
The county will host a Public Community Meeting about Shoal Creek Trunk Sewer Project Section I.
Meeting Information:
Tuesday, May 19
6:30 – 8 p.m.
Community Achievement Center
4522 Flat Shoals Parkway
Decatur, GA
Information also can be obtained by calling the DWM Project Information Line at 1-800-986-1108 or emailing projectinfo@dekalbcountyga.gov with questions and concerns.
Normal construction hours will be from 7 a.m. to 7 p.m., Monday through Friday, excluding major holidays. An increase in construction-related noise and traffic during work hours should be expected.
The county will host a Public Community Meeting about Shoal Creek Trunk Sewer Project Section I.
Meeting Information:
Tuesday, May 19
6:30 – 8 p.m.
Community Achievement Center
4522 Flat Shoals Parkway
Decatur, GA
Information also can be obtained by calling the DWM Project Information Line at 1-800-986-1108 or emailing projectinfo@dekalbcountyga.gov with questions and concerns.

Project Objective
The Shoal Creek Trunk Sewer Replacement Project is designed to improve the watershed system in DeKalb County, Georgia. Impacted stakeholders can learn about the project below:
Section 1 Project Start Date: 2026
Section 1 Project End Date: 2029
Section 2 Project Start Date: 2029
Section 2 Project End Date: 2031
3B PFL Project Start Date: 2032
3B PFL Project End Date: 2033
3A PFL Project Start Date: 2034
3A PFL Project End Date: 2035
Timeframe: 9 years from start to finish
- Project and Meeting Notification Letter
- Project Meeting Notification Letter per Cherry Ridge Community
- Project Meeting Notification Letter per Midway Woods Community
- FAQs
- Fact Sheet